West Kelowna transmission line delays frustrating for council

Plans to twin existing transmission line from Merritt appear to be too costly
19366128_web1_181130-KCN-newpowerline2
BC Hydro will not continue with a second transmission line project for West Kelowna, despite an announcement made in 2015 by former B.C. premier Christy Clark that the project would proceed. (File photo)

City councillors in West Kelowna voiced their frustration to BC Hydro officials on Tuesday night after it was revealed a proposed plan to build a secondary transmission line to West Kelowna continues to change.

At the meeting, BC Hydro stakeholder relations manager Rachelle Trent informed council that a decision to twin an existing transmission line between Merritt and West Kelowna was no longer the most feasible option.

Instead, she said the provincial agency recently completed a new six-month feasibility study to look at ways it could upgrade the existing line instead of building a new one from Merritt.

sa国际传媒淭he West Kelowna transmission project is in BC Hydrosa国际传媒檚 current capital plan and continues to move forward. Both new transmission line alternatives (building a second transmission line) and a resiliency alternative (increasing the resilience of the current line) are on the table,sa国际传媒 wrote Dag Sharman, community relations manager for BC Hydro.

He said BC Hydro is also looking at whether it is feasible to build a secondary transmission line into West Kelowna from other areas, including a new transmission line on the west side of Okanagan Lake, connecting Westbank to Vernon, a transmission line connecting Westbank to Nicola and/or a new transmission line across Okanagan Lake, connecting Westbank to the FortisBC system.

sa国际传媒淏C Hydro understands that redundancy is a priority for the communities and we want to confirm that building a new, second transmission line is being considered,sa国际传媒 wrote Sharman.

sa国际传媒淪ince the leading alternative was identified in 2016, the cost estimate to build the new transmission line has increased. Itsa国际传媒檚 prudent that we review the cost estimate and relook at all alternatives available to us to ensure we make the decision that will ensure we continue to deliver clean, reliable electricity to the West Kelowna and Peachland areas while keeping rates low for our customers.sa国际传媒

READ MORE: Westside to finally get second electricity transmission line

West Kelowna city councillor Stephen Johnston said the delays have been frustrating.

sa国际传媒淭his project has been a conversation with the Central Okanagan Regional District since 2007,sa国际传媒 said Johnston.

sa国际传媒淭o get through this whole process since 2015, and then throw it all back on the table and say sa国际传媒榊eah, wesa国际传媒檙e actually going to look at this whole resiliency thingsa国际传媒 four years after the project was initiated, one cansa国际传媒檛 help but think were just being monkeyed around.sa国际传媒

As part of the possible improvements, Trent said culverts would be built around existing transmission poles in grasslands along the line to help prevent them from catching on fire in dry conditions.

Improving access roads around the line in the event of an emergency and improving the linesa国际传媒檚 drainage from ice and wind were other proposed improvements.

After the announcement, councillor Doug Findlater said improving access roads around the line wouldsa国际传媒檛 fix the problem in the event of an emergency.

sa国际传媒淢any of our equipment failures have been due to wildfire. These incidents have been very local and high in the mountains.sa国际传媒

sa国际传媒淒uring these instances, BC Hydro officials have driven on little access roads in the middle of the night trying to find these failures.

sa国际传媒淭hey couldnsa国际传媒檛 find them.sa国际传媒

Councilor Jason Friesen said more effort needed to be made by hydro officials to solve the problem.

sa国际传媒淲e have one line and we have safety issues,sa国际传媒 said Friesen.

sa国际传媒淚 donsa国际传媒檛 want to hear that you have our best interests on this project, because you donsa国际传媒檛.

sa国际传媒淲e have patients that are on oxygen tanks that last for two hours. We have elderly people that are lying in beds that cansa国际传媒檛 afford to get cold or that cansa国际传媒檛 afford to get pneumonia or theysa国际传媒檒l die.sa国际传媒

Sharman said the Crown corporation will make a final decision on how to advance the energy project next year.